UDC 622.271.3:012.3.001:622.281.424
Yerkin Iskakov, Ph. D., Master of
Mining Kazakh National Technical University named after K.I. Satpayev.
Construction of stations of columned type of the
subway in Almaty.
Construction
of stations by underground way belongs to the most difficult types of works in
subway construction as it is connected with the device of a complex of the
interconnected constructions and disclosure of developments of big section.
Construction conduct in such technological sequence not to allow a deposit of
the terrestrial surface, buildings dangerous to safety and constructions, and
also a deposit of underground communications of the municipal economy located
above station. Motions of
the soil massif and a flash of a roof of developments have to be minimum.
At
construction of stations by underground way use usually working mine trunks,
but also inclined (esñalator) tunnels, and in some cases ventilating
trunks and distillation tunnels can be used.
The
main (platform) part of station constructs the line method providing a
continuity of maintaining all complex of works in strict technological
sequence. Thus use the principle of the maximum combination of separate types
of works in time. Such organization of works provides the smallest duration of
construction.
Three-vaulted
stations construct by a consecutive driving of three station tunnels. At first construct lateral tunnels, and then
— average.
In
not rocky soil putting pressure from a forehead of a face, a construction
conduct with a preliminary driving the pilot tunnels, by means of boards or banquette way.
For
a possibility of management of the provision of designs an cast in-situ lining
on station distance a driving of tunnels of three-vaulted stations with
monolithic ferroconcrete cast cast in-situ lining
conduct in one direction. At a construction of stations in unstable soil a
driving of the second (on sequence of a construction) a lateral tunnel not less
than 30 m concerning the first, and an average — with lag conduct with lag not
less than 50 m concerning the second lateral tunnel.
The
way of development and face fastening at construction of stations establish
depending on properties of developed soil. At a driving of station tunnels in
the banquette way soil develops tunnel
excavators with a ladle of active action.
Development
of a face at a driving of separate station tunnels of three-vaulted stations
conduct, as a rule, on width of 1 m.
Construction
of an cast in-situ lining of lateral tunnels of three-vaulted stations conduct
usually closed rings, and with the party turned to average part of station,
along with usual elements establish the elements entering subsequently into
structure of the main bearing design (a column, randbalka and basic beams).
In
places of future passes in an cast in-situ lining carry out temporary fastening.
At
the device of a monolithic ferroconcrete cast in-situ lining of lateral tunnels only vertical
ellipticity (increase in vertical diameter) is allowed.
Average
station tunnel pass with acceptance of necessary measures for prevention of
deformations of an cast in-situ lining
of lateral tunnels and shifts of columns.
For
this purpose in lateral tunnels establish steel racks from metal pipes, and on
the average a tunnel executions from metal pipes.
Monolithic
concrete or ferroconcrete elements of an cast in-situ lining of station erect separate sites with
application, as a rule, the mobile mechanized
or inventory collapsible timbering’s and other specialized equipment
(pneumoconcrete placers, concrete pumps, mechanical of a timbering).
Length
of sites of concreting depends on the accepted way of a construction of station
and construction of elements of an cast in-situ lining.
Sequence
of a construction of station of columned type on the NATM technology with a
ferroconcrete monolithic cast in-situ lining
the following:
• pass lateral station tunnels
in the way of the bottom ledge with lag of a face of the second tunnel not less
than 30 m concerning the first;
Driving
of the second (on sequence of a construction) a lateral tunnel conduct with a
reinforcement of the arch of the first tunnel vertical racks from metal pipes
with a diameter of 300 mm, establishing through 1,5 m on two racks with a
crossbar.
Racks
establish on 15 m ahead concerning a face of the second tunnel. Racks of
temporary fastening in the second lateral tunnel establish before a
construction of an average tunnel.
• carry out in sequence from the cross camera a waterproofing of
lateral station tunnels the PVC film;
• carry out step by step a
monolithic ferroconcrete cast in-situ lining of lateral station tunnels;
• carry out in lateral station
tunnels step by step monolithic ferroconcrete columned and crossbar ranks;
Each
part concrete in 2 stages. At 1 stage concrete a ferroconcrete tray at length
of a part of a mobile timbering.
Concreting
of a site of a wall and the arch conduct continuously by means of the pneumonic
supercharger. Breaks when concreting (on horizontal seams) shouldn't exceed 2
h.
The
device of working seams is allowed only on a horizontal axis of a tunnel. At the same time conduct concreting of a
site of a columned and crossbar row continuously by means of the pneumonic
supercharger. Breaks when concreting (on horizontal seams) also shouldn't
exceed 2 h.
After
a set concrete of design durability makes concreting of the following part.
• calotte an average station
tunnel from the cross camera pass the first 9 m in the mountain way, and the
subsequent part pass the NATM method on 7 m in temporary shot concrete fix;

Figure 2 - Technology of a driving of station of the subway of NATM
• carry out in sequence from the cross camera a
waterproofing of the top arch
part of an average station tunnel the PVC film.
• carry out step by step part on
10 m a monolithic ferroconcrete cast in-situ lining of the top arch of an average tunnel with the device of knot of
an bear on on columned and crossbar ranks of lateral tunnels;
• pass in temporary shot
concrete fix strosse an average station
tunnel on the first part – 9 m, on the subsequent – 7 m with installation of
executions of temporary fastening from the metal pipes Æ300 mm;
• carry out a waterproofing of a
part of the lower arch part of an average station tunnel a method of drawing
waterproofing composition;
• carry out step by step part on 8
m a monolithic ferroconcrete cast in-situ lining of the return arch of an average tunnel with the device of knot
of interface of the arch with a basic beam of a columned and crossbar row;
• carry out dismantle of executions
temporary fix.

Figure 2 -
Baikonur station construction with advancing supports and the NATM elements.
The
device of the next part of a monolithic ferroconcrete cast in-situ lining of an average tunnel carry out after a set
75% of durability of concrete of the previous part. Surface shot concrete,
reinforcing frameworks of a part carefully level, carry out concreting.
Temporary
filling of apertures investigate in the course of a driving and development
calotte an average tunnel. It gives the chance to give out developed soil and
to give materials through lateral tunnels.
In
the course of construction continuous control of deformations is conducted fix.