By virtue of natural conditions, a place of elaboration of quarrying and their agricultural landscapes poorly protected from external human impact. Conducting large-scale economic activities related to the conversion of the existing natural conditions lead to changes in the formation water resources. Therefore, the conservation and protection of natural landscape features in the areas of economic load is very important.

The construction of quarries can reduce overall water resources due to additional losses, the value of which in some areas is a considerable share of the total volume of irreversible water.

Due to the high level of mechanization of mining operations is water pollution (namely quarry waters) by petroleum products. Quarry water formed as a result of falling groundwater and surface natural water in the mining elaboration, are subject to contamination in the process of extracting a mineral resource. Quarry waters pollution occurs mainly finely dispersed weighted parts of minerals, placing rocks that formed at: drilling blast holes and test pits; crushing rocks explosive manner; work anadromous and cleansing combines; bootable and transport operations.

One such factor is the quarry of building materials, which operates within Hotyslav deposits of chalk and sand. Hotyslav quarry located in the Republic of Belarus at a distance of 0.25 km from the border with Ukraine. Hydrogeological conditions are unfavorable quarry – chalk watered at all useful power in some places groundwater level in low-flow periods is set at depths of 1.0 – 1.5 m.

Significant amounts of mining operations, which are designed to Hotyslav quarry, accompanied by a powerful pumping (27.5 thousand cubic meters/day), which will negatively impact on water resources and the surrounding protected areas.

 

Dewatering planned to carry out into the river Rita by means of discharge channels directly from a quarry and support throughout the service life decline in ground water up to 45 meters. The territory of quarry entirely located within the catchment area of the river Rita, which is 1730 square meters (with its tributaries). The length of the river is 24.5 km.

Establishing modern hydrological and hydrogeological conditions within the investigated territory occurs in conditions disturbed holding of drainage reclamation in the 70 80's the last century. Land reclamation has caused an increase in the maximum annual flow of the river Rita is 1.5 times, and the minimum flow – 2.2 times. In basin of the river Rita influenced by drainage amelioration since the mid 70's last century installed and there is still weakly disturbed regime of groundwater, and their level throughout the territories of Ukrainian and Belarusian Polesie parts were down on 0.4 0.6 m.

Thus, one of priority directions water management in the conditions of elaboration of quarrying is the improvement existing and development new approaches and tools of mining operations and environmental regulation for the conservation of productive natural environment for the further development of water management.

 